What is takt time?

Takt time says how often one unit has to be completed to meet customer demand. It does not show how fast the line can run but how fast it has to run, which is why it is calculated and not measured.

The word comes from the German “Takt”: beat, rhythm. With a takt time of 45 seconds, one good unit has to leave the end of the line every 45 seconds. Slower misses demand; faster builds stock.

How to calculate takt time

Takt time = Net production time ÷ Customer demand

Time and demand must describe the same period: the time of a shift is divided by the demand of a shift, the time of a day by the demand of a day. Convert the time to seconds to get the result in seconds.

ItemPart of net production time?Why
Meal and tea breaksNo, taken offThey are planned; nothing is expected to be made
Planned meetings, cleaning, planned maintenanceNo, taken offThey have a fixed place in every shift
Breakdowns and waiting for materialYes, left inThey are unplanned; takt time must not hide the loss

Demand is the number of good units the customer wants. The quantity in the production plan, the capacity of the machine and last month’s output are not demand.

Takt time calculator

Enter the numbers of your own shift; the result updates as you type. The values it opens with belong to the example below. If you put the measured cycle time of your slowest station in the last field, the calculator also shows whether that pace meets demand.

Takt time

45seconds

Net production time
450 minutes
Pace required
80 units/hour
Capacity at this cycle time
529 units

The cycle time is longer than the takt time: at this pace the shift ends 71 units short of demand.

Worked example

An assembly line with four stations takes 30 minutes of planned breaks in a 480-minute shift. The customer wants 600 units per shift.

StepCalculationResult
Net production time480 − 30450 minutes
In seconds450 × 6027,000 seconds
Takt time27,000 ÷ 60045 seconds
Pace required3,600 ÷ 4580 units/hour

One unit has to leave the line every 45 seconds. Now look at the measured cycle times of the stations:

StationCycle timeAgainst takt time
136 seconds9 seconds to spare
242 seconds3 seconds to spare
351 seconds6 seconds over
440 seconds5 seconds to spare

A line runs at the pace of its slowest station. Station 3 gives one unit every 51 seconds, so the shift ends with 27,000 ÷ 51 = 529 units, 71 short of demand. The other three stations being fast does not close that gap; it only piles up work in progress in front of station 3.

When demand rises

If the customer starts asking for 720 units per shift, the numbers for the same line change:

Demand of 600 unitsDemand of 720 units
Takt time27,000 ÷ 600 = 45 seconds27,000 ÷ 720 = 37.5 seconds
Pace required80 units/hour96 units/hour
Minimum operators169 ÷ 45 = 3.76 → 4169 ÷ 37.5 = 4.51 → 5

The line is the same line, yet three of its four stations are now over takt time. The options are clear: spread the work over five stations or add working time. If the same 720 units are spread over two shifts, net time becomes 900 minutes and takt time is 54,000 ÷ 720 = 75 seconds.

Takt time vs cycle time

The two are often confused because both are “seconds per unit”. The difference is where they come from: takt time comes from the customer, cycle time from the station.

What it tells youHow you get itIn the example
Takt timeThe pace demand asks forNet production time ÷ demand45 seconds
Cycle timeHow long the station takes to complete one unitMeasured at the station36 to 51 seconds
Total work contentAll the labour that goes into one unitThe sum of the cycle times169 seconds

The rule is simple: the cycle time of every station should equal the takt time or be slightly shorter. If it is longer, demand is not met. If it is much shorter, the station waits or makes more than is needed.

On the floor, takt time earns its keep in three places:

When cycle time exceeds takt time

Before you turn to overtime, work through these in order:

  1. Break the work into elements. Write down the work of the station that is over, step by step, and time each step. Seconds that add no value, such as walking, searching, reaching and waiting, are the first to go.
  2. Move work to a station with time to spare. In the example, moving a 7-second step from station 3 to station 1 gives 43, 42, 44 and 40 seconds. Total work content is still 169 seconds, but no station is over 45 seconds any more.
  3. Check the number of operators. The minimum number of operators is total work content divided by takt time: 169 ÷ 45 = 3.76, so 4 operators. If the result is more than the people you have, balancing is not enough; you have to reduce the work content or add a station.
  4. Make the new split the standard. If the step that moved is not written into the work instruction, the line drifts back to its old arrangement within days.

Common mistakes in the calculation

Measuring cycle time properly

Takt time is calculated at a desk; the cycle time it is compared with is measured on the floor. A single stopwatch reading misleads: the operator knows they are being watched, and the reading may fall on a good moment of the day. Time at least ten cycles, repeat at different hours and with different operators, and note unusual cycles together with their causes.

With Deskval Workbench the measuring happens by itself: while the operator does the job by following the steps on the screen, job times and stop and reject reasons are recorded. To compare cycle time with takt time you then have the data of every shift, not one reading. See Workbench

Frequently asked questions

What does takt mean?

“Takt” is German for beat or rhythm. Takt time is the beat of customer demand: the time within which one unit has to be completed for demand to be met.

How is cycle time calculated?

Cycle time is measured, not calculated: it is the time from one unit being finished to the next one being finished. For a quick check you can divide the net working time of a period by the units made in it; that gives an average which includes the stops.

What is the ideal cycle time?

It is the shortest cycle time a station can reach when it runs without losses, and it is used in the performance component of OEE. Takt time comes from demand; ideal cycle time comes from what the station is capable of.

How often should takt time be updated?

Whenever demand or working time changes: a new order period, a change in the number of shifts, a change in breaks. Where demand fluctuates, a weekly or monthly calculation is common.