Deskval

Production Tracking Sheet: Example and Free Excel Template

At its simplest, production tracking is a one-page sheet with the target and the actual count of every hour side by side. This guide covers the columns of the sheet, a completed shift as an example and how to use it on the floor; you can download the Excel template too.

6 min readUpdated 24 November 2026

What is production tracking?

Production tracking means seeing, while the shift is still running, where a line or a station stands against its plan. It answers three questions: how many units should have been made by now, how many were made, and what caused the gap?

Its simplest tool is the hour-by-hour production tracking sheet. The target and the actual count of every hour sit side by side, and the reason for an hour that fell short is noted in the same row. A problem shows up in the hour it happens, not at the end of the shift.

What goes on a production tracking sheet?

The top of the sheet names the date, the shift, the line or station, the product and the shift leader. Below it there is one row per hour:

ColumnWhat you writeWhat it is for
HourOne-hour slots such as 08:00–09:00Shows in which hour the loss happened
TargetUnits that should be made in that hourAn hour with a break gets a lower target, so the comparison is fair
ActualGood units made in that hourCounts what can be shipped, not the scrap
GapActual − targetShows how that hour went on its own
Total gapThe gap from the start of the shift to that hourShows whether the shift will reach its target
ScrapDefective units set aside in that hourSeparates the quality loss from the output loss
StopsTime the line stood still, in minutesShows how much of the gap comes from stops
CommentThe reason and what was doneWhat you need to keep the same problem from coming back

The hourly target follows from takt time:

Hourly target = working time in that hour (seconds) ÷ takt time (seconds)

With a takt time of 45 seconds the target of a full hour is 3,600 ÷ 45 = 80 units. In the hour with a half-hour meal break the working time is 1,800 seconds, so the target is 1,800 ÷ 45 = 40 units.

Example: one shift, hour by hour

A line that assembles socket modules runs the 08:00–16:00 shift. There is a 30-minute meal break, the shift target is 600 units and takt time is 45 seconds. At the end of the shift the sheet looks like this:

HourTargetActualGapTotal gapScrapStops (min)Comment
08–098070−10−1025Start-of-shift setup
09–1080800−1000
10–118077−3−1310Scratched cover
11–128055−25−38018Screw feeder jammed
12–1340400−3800Meal break
13–148078−2−4010Missing screw
14–158059−21−61312Cover bin late
15–1680800−6100
Total600539−61735

The shift ended 61 units short of its target of 600. The sheet tells you this:

More than three quarters of the loss comes from three stops, and the largest has a single cause, the screw feeder. The first job of the next day is clear. Without the sheet, all you would have at the end of the day is “539 units”.

Free production tracking sheet (Excel)

Daily production tracking sheet (Excel)

Prints on one A4 landscape page. It holds a blank sheet, the completed example above and a short page on how to use it, and it works out the gaps, the totals, target attainment and scrap rate for you.

Download the sheet (.xlsx)

Free, no sign-up. Print it and post it at the line, or fill it in on screen.

How to track production in six steps

  1. Split the target into hours. Turn the shift target into hourly targets with takt time, and lower the target of hours with a break. Write the targets on the sheet before the shift starts.
  2. Post the sheet at the line. It belongs where the operator and the shift leader see it as they walk by. A sheet in a drawer is a report, not tracking.
  3. Write at the end of every hour. Good units, scrap and minutes stopped go on the sheet as soon as the hour is over. A sheet filled in from memory at the end of the shift loses the reasons.
  4. Write the reason plainly. “Breakdown” or “material” is not a reason. “Screw feeder jammed” and “cover bin arrived late” are reasons someone can act on the next day.
  5. React within the hour. An hour below target is the signal for the shift leader to go to the line. If the total gap grows, do not wait; call maintenance, logistics or quality in that hour.
  6. Add it up every week. Count the reasons on a week of sheets and rank them by the units they cost. The top one or two are the subject of your improvement work.

Four common mistakes

When is it time to move from Excel to a tracking system?

A paper sheet and Excel do well on one line with one product. As lines, products and shifts are added, collecting the data becomes a job of its own:

Paper sheetExcelProduction tracking system
How data gets inBy hand, once an hourBy hand, mostly at the end of the shiftBy itself, from the station, as the work is done
When you see the statusAt the line, in that hourWhen the file is openedAt once, from anywhere
ReasonsFree textFree text or a listA chosen reason, with its duration
Looking backSheets are counted by handFiles have to be mergedDone on records that already exist
When it is enoughOne line, few productsA few lines, disciplined data entryMany lines, many products, a need for traceability

Tracking by hand has reached its limit when one of these shows: sheets are filled in all at once at the end of the shift, the weekly report takes hours to prepare, the same count differs between two files, or a customer asks which unit was made when and by whom. When you want to follow stops and scrap separately, the next step is OEE.

With Deskval Workbench this record comes into being as the work is done: while the operator follows the steps on the screen, job times, stop and reject reasons, good and defective counts are recorded by themselves, with no forms to fill in. See Workbench

Frequently asked questions

What is a production tracking system?

An arrangement that collects output, stops and their reasons while the work is done and compares them with the target. It can be a paper sheet or software that takes the data from the station by itself; the difference lies in how the data is collected.

Can you track production in Excel?

Yes. On one line with a limited number of products an hourly Excel sheet is enough. As lines and products are added, typing the data in and merging files gets hard; that is the point to move to a system that takes the data from the station.

How often is a daily production tracking sheet filled in?

Once an hour, at the end of the hour. Jobs with a long cycle time also use two-hour slots. A sheet filled in all at once at the end of the shift does not capture the reasons.

Is a production tracking system the same as an MES?

Production tracking is one of the functions of an MES (manufacturing execution system). An MES also manages work orders, traceability and quality records. For a plant that only wants to follow counts and stops, tracking is the first step on the way to an MES.